Nov 28 - Dec 9, 2022
Monday, December 12, 2022 in 2022

It’s a busy time of year and we had a lot of other work going on in the past two that impacted what we were able to complete in terms of development and design work. For development, we closed 3 points and 13 issues for a rolling velocity of …
Nov 14 - Nov 25, 2022
Monday, November 28, 2022 in 2022

We completed a couple of major things before the Thanksgiving holiday — completed the PPA migration to PUL infrastructure, and completed the dataset export work for PGP. We completed 12 development points for a rolling velocity of 5.33 - the low …
Oct 31 - Nov 11, 2022
Monday, November 14, 2022 in 2022
The points completed in the last iteration are low due to staffing and the fact that our work has been focused on migrations and bug fixes. Our rolling velocity is 7.3, but that may be artificially inflated by the high point total three iterations …
Oct 17 - Oct 28, 2022
Monday, October 31, 2022 in 2022

This iteration marked the end of the charter for year 2 of the CDH Research Partnership on Princeton Geniza Project (PGP). We released version 4.10 of PGP, with some bugfixes and small search and data improvements. We’re ramping up on other …
Oct 4 - Oct 15, 2022
Tuesday, October 18, 2022 in 2022

Another high point iteration, as we made the final push to finish work for the CDH/Geniza Research Partnership. For development, we closed 18 points across 31 issues, resulting in a rolling velocity of 18.67 (exactly the same as last iteration). …
Sep 19 - Sep 30, 2022
Monday, October 03, 2022 in 2022
We had a massive iteration, as we make a push to complete the major remaining deliverables on the Princeton Geniza Project before the partnership grant ends. We also made some small progress on the Lenape timetree project. We completed 48 total …
Sep 5 - Sep 16, 2022
Monday, September 19, 2022 in 2022

Our primary focus continues to be Princeton Geniza Project, but we’re also starting to track work on the Lenape Timetree project, and had a few releases for other projects for maintenance and other updates. We closed 14 development points and …
Aug 23 - Sep 3, 2022
Tuesday, September 06, 2022 in 2022

We had another very productive iteration; we had 18 points total accepted on the Princeton Geniza Project, and we completed 18 development points. This results in a rolling development velocity of 15.7 points, continuing our upward trend. We closed a …
Aug 8 - Aug 19, 2022
Monday, August 22, 2022 in 2022

We had a productive iteration, making good progress on both Princeton Geniza Project and Princeton Prosody Archive (PPA). We closed 13 development points (18 issues); with three strong iterations in a row, we’re up to a rolling development …
Jul 25 - Aug 5, 2022
Monday, August 15, 2022 in 2022

Belated iteration report, due to vacations last week. We closed a lot of development work (16 points, 23 issues); this is likely due to the transcription editor functionality that was tested and accepted and the number of small chores in the final …