Report on iteration Jul 24, 2023 — Aug 4, 2023 (includes all issues completed before Aug 7, 2023).

We’re a small team working on multiple projects at once. We made significant progress on the geotaste tool, and work has ramped up in intensity with plans to complete the prototype by the end of August. We also continued making progress on the simulations for the Simulating Risk project, completing a revision to one simulation and a new histogram chart. We also completed some maintenance work on the CDH website to upgrade some dependencies, and released a micro version with those changes.

Demos

Screenshot showing resent progress on the Geotaste mapping tool

Screenshot showing resent progress on the Geotaste mapping tool

Screenshot showing Simulating Risk interactive Mesa display of the ‘Risky Bet’ simulation in progress with the new histogram chart.

Screenshot showing Simulating Risk interactive Mesa display of the ‘Risky Bet’ simulation in progress with the new histogram chart.


Active projects

Releases

Velocity

Development

4 points, 13 issues. Rolling velocity: 7.67

Design

0 points, 0 issues. Rolling velocity: 2