Aug 24 - Sep 4, 2020

Report on iteration Aug 24, 2020 — Sep 4, 2020 (includes all issues completed before Sep 7, 2020).

The last iteration we continued to spend time on project maintenance and updates. Closed issues on Startwords and the pucas release are continuing and closing out work from the previous iterations. Active work this iteration that is incomplete and not reflected in the closed tickets include django/mezzanine upgrades for cdhweb, and refactoring PPA to remove an outdated SolrClient dependency and use parasolr instead. We also have now migrated our first repositories to use main as the production branch name.

Over the last iteration we also wrote a new limited support agreement, which was adapted and simplified from the “Built by CDH” Long Term Service Agreement in order to offer minimal support for the PEMM Incipit Search Tool for a limited term (1 year, renewable for a second year). The limited support agreement for PEMM goes into effect today.

Demos

Screenshot of new 404 page design for Startwords

Screenshot of new 404 page design for Startwords


Active projects

Releases

Velocity

Development

5 points, 7 issues. Rolling velocity: 2.33

Design

3 points, 1 issue. Rolling velocity: 1


Closed issues by project